The Kiln, Wisborough Green: April-May 2017 Now the demolition has finished and the site is cleared, groundworks can begin with footings being dug, concrete poured and oversight in place.
The Kiln | Stage One
The Kiln, near Wisborough Green: March 2017 The site is now prepared so that demolition can commence.
Liphook | Stage Seven
External works including the driveway, terraces and the landscaping of the one acre site are now well underway, providing the finishing touches for this beautiful location.
Liphook | Stage Six
Kitchen furniture is installed and then appliances and floor finishes are fitted as the house nears completion.
Liphook | Stage Five
As the roof tiling nears completion plastering, decorating and second fix is the focus of activities.
Liphook | Stage Four
As the house becomes water tight, the screed is pumped in and first fix commences.