External and internal works now continue in parallel through September and October.
The Kiln | Stage Five
Once the frame construction is complete, the floor insulation and underfloor heating piping is installed before the floor screed is pumped in. With the flooring in place, first fix can then begin in earnest.
The Kiln | Stage Four
The timber pre-insulated frame is installed during August, and work immediately begins to make the structure water-tight.
The Kiln | Stage Three
During June and July, ground works were completed and the slab installed ready for the timber frame to be erected. Progress will be swift as we progress with the roof to make the house watertight so that first fix can begin.
The Kiln | Stage Two
The Kiln, Wisborough Green: April-May 2017
Now the demolition has finished and the site is cleared, groundworks can begin with footings being dug, concrete poured and oversight in place.
The Kiln | Stage One
The Kiln, near Wisborough Green: March 2017
The site is now prepared so that demolition can commence.