Liphook | Stage Three

December 19, 2016 By Rob Hall

The timber frame has now been erected so the scale of the house and the fantastically proportioned rooms can now all be seen, including the beautiful oak barn room and entrance area.

liphook-stage-3-architectural-homes

liphook-stage-3-architectural-homes-1

liphook-stage-3-architectural-homes-2

liphook-stage-3-architectural-homes-3

Work is now progressing on adding felt and battens to the roof structure so first fix can commence. Windows are also being fitted to the main house elevations.

liphook-stage-3-architectural-homes-4

liphook-stage-3-architectural-homes-5

Filed Under: Liphook

Liphook | Stage Two

December 19, 2016 By Rob Hall

Ground work started with excavating footings before pouring concrete and then moving onto installing the brick courses to DPC level followed by the concrete slab. Drainage channels have also been dug for foul and rain water.

PineRidge-liphook-1-architectural-homes

PineRidge-liphook-2-architectural-homes

PineRidge-liphook-3-architectural-homes

PineRidge-liphook-4-architectural-homes

 

 

Filed Under: Liphook

Liphook | Stage One

December 13, 2016 By Rob Hall

Demolition of the existing 1950s house is now complete and the site has been opened up through the approved removal of a number of trees which means the full extent of the one acre site can now be seen.

liphook-stage-1-architectural-homes

liphook-stage-1-architectural-homes-2

liphook-stage-1-architectural-homes-3

Filed Under: Liphook

Bosham | Stage Six

December 13, 2016 By Rob Hall

Final fit out is underway including bathrooms, kitchen and utility.

bosham-stage-6-architectural-homes-4

bosham-stage-6-architectural-homes-3

bosham-stage-6-architectural-homes-2

Meanwhile external works include driveways and paths being laid now the scaffold has been fully removed. The ground sourced heat pump is commissioned and the house is nearly ready for occupation.

bosham-stage-6-architectural-homes

Filed Under: Bosham

Bosham | Stage Five

December 13, 2016 By Rob Hall

Roofing is now complete so external works focus on cladding and render.

bosham-stage-5-architectural-homes

Meanwhile internally, second fix is well underway including fitting of the handmade oak staircase and tiling is in full flow.

bosham-stage-5-architectural-homes-2

bosham-stage-5-architectural-homes-3

bosham-stage-5-architectural-homes-4

bosham-stage-5-architectural-homes-5

Filed Under: Bosham

Bosham | Stage Four

December 13, 2016 By Rob Hall

External and internal works continue apace with roofing, plaster, decoration and basement fit out all taking place.

bosham-stage-4-architectural-homes

bosham-stage-4-architectural-homes-2

bosham-stage-4-architectural-homes-3

bosham-stage-4-architectural-homes-4

Filed Under: Bosham

  • « Previous Page
  • 1
  • 2
  • 3
  • 4
  • 5
  • 6
  • Next Page »
  • Home
  • About
  • What We Do
  • Projects
    • Commissions
    • Land Wanted
    • Completed Projects
  • Testimonials
  • Contact Us

Copyright © 2025 The Architectural Building Company · Website by Fresh Eyes Agency