External and internal works now continue in parallel through September and October.





The Architectural Building Company
New Homes West Sussex
By Rob Hall
External and internal works now continue in parallel through September and October.





By Rob Hall
Once the frame construction is complete, the floor insulation and underfloor heating piping is installed before the floor screed is pumped in. With the flooring in place, first fix can then begin in earnest.




By Rob Hall
The timber pre-insulated frame is installed during August, and work immediately begins to make the structure water-tight.




By Rob Hall
During June and July, ground works were completed and the slab installed ready for the timber frame to be erected. Progress will be swift as we progress with the roof to make the house watertight so that first fix can begin.




By Rob Hall
Now the demolition has finished and the site is cleared, groundworks can begin with footings being dug, concrete poured and oversight in place.



By Rob Hall
The site is now prepared so that demolition can commence.