Vine Cottage | Rapid Progress Continues Through January

February 17, 2015 By Rob Hall

vine-cottage-internal-jan

vine-cottage-plastering

vine-cottage-external-brick

vine-cottage-roofing

vine-cottage-roof-tiles

vine-cottage-kitchen-construction

Filed Under: Vine Cottage

Vine Cottage | November 2014

December 11, 2014 By Rob Hall

Throughout November, work has continued with the construction of the garage and utility rooms whilst preparations to receive the main house timber frame have been completed.

vine-cottage-garage-utility

The roof is now almost complete and the structure ready to be connected to the main house frame in early/mid December.

vine_cottage_roof_trusses

vine-cottage-utility-roofing

The trays for the solar PV panels have also been fitted to the garage roof. These are part of the whole house energy system which will create a completely free energy supply for electricity, heating and hot water.

vine-cottage-solar-panel-trays

Filed Under: Vine Cottage

Vine Cottage | Laying the Foundations

November 3, 2014 By Rob Hall

Work is now well and truly underway at our latest project in West Lavington.

With the original house demolished, the team have also cleared the site of overgrown borders and felled a number of trees so we can maximise the views from this fantastic position.

vine-cottage-west-lavington-site

We have also adapted the driveway access from Highstanding Lane, so that there is a wider driveway with very shallow gradient.

vine-cottage-west-lavington-pipework

All groundworks and drainage are now complete.

vine-cottage-west-lavington-concrete-pouring

vine-cottage-west-lavington-groundworks

Our bricklayers are focussed on completing the garage in brick before the main timber frame arrives on site on 5th December.

vine-cottage-west-lavington-garage-construction

Filed Under: Vine Cottage

East Harting | Weeks 20-24

August 14, 2014 By Rob Hall

Final internal fitting, glazing of oak structures and garden landscaping completes the project.

The house really comes together in these final weeks.

The big oak structures come to life as the glazing is installed, skirting boards and walls are given their final coats of paint and door handles are fitted.

east-harting-house-glazing

The solid oak front door is installed and glass balustrades are fitted to the staircase and landing areas.

Bathrooms are grouted and cabinets fitted to complete the final touches inside.

Externally, the garden landscaping progresses, firstly with structural shape in the form of pathways and large indian stone terraces and then through extensive planting and creation of new lawns.

east-harting-house-landscaping

Final tasks include laying the shingle driveway, installing doors to the garage store and cleaning the house ready for it’s new owners.

Filed Under: East Harting

East Harting | Weeks 16-20

August 14, 2014 By Rob Hall

Second fix, tiling, kitchen and bathroom fit out, whilst external works continue.

The busy period continues with a host of trades working together as both internal and external works progress towards their conclusion.

Second fix plumbing and electrics follow on from plastering in conjunction with tiling, bathroom and kitchen fit out.

east-harting-house-kitchen-fitout

The oak staircase and ballustrading is installed and final internal joinery including door hanging and wardrobe fitting is completed, whilst the decorators work they way around the house, room by room.

At the end of this period, Kahrs oak flooring and large scale ceramics are laid to the ground floor and carpets to the first floor bedrooms.

east-harting-house-oak-flooring

Externally, the roof is completed, as are the external walls of stone and cedar cladding.

east-harting-house-external-brickwork

 

 

Filed Under: East Harting

East Harting | Weeks 11-15

August 14, 2014 By Rob Hall

First fix, external works and plaster.

This is a really busy time on site with a peak labour force exceeding twenty during this period.

First fix electrics and plumbing are installed, as are the window frames and glazing, whilst external stonework and timber cladding progresses rapidly.

east-harting-house-cedar-cladding

Plastering follows first fix along with internal joinery.

east-harting-house-plastering

At the same time, the underfloor heating system is installed and the system pressure tested before the flooring screed is pumped into the ground floor.

east-harting-house-underfloor-heating

The oak garage structure also takes shape whilst the beautiful stone external garden walls progress.

east-harting-house-timber-garage

east-harting-house-garden-wall

Filed Under: East Harting

  • « Previous Page
  • 1
  • …
  • 3
  • 4
  • 5
  • 6
  • Next Page »
  • Home
  • About
  • What We Do
  • Projects
    • Commissions
    • Land Wanted
    • Completed Projects
  • Testimonials
  • Contact Us

Copyright © 2025 The Architectural Building Company ยท Website by Fresh Eyes Agency