First fix, external works and plaster.
This is a really busy time on site with a peak labour force exceeding twenty during this period.
First fix electrics and plumbing are installed, as are the window frames and glazing, whilst external stonework and timber cladding progresses rapidly.
Plastering follows first fix along with internal joinery.
At the same time, the underfloor heating system is installed and the system pressure tested before the flooring screed is pumped into the ground floor.
The oak garage structure also takes shape whilst the beautiful stone external garden walls progress.