East Harting | Weeks 1-5

August 14, 2014 By Rob Hall

Demolition and Ground Works.

Work commences in March, first with the demolition of the old bungalow and removal of foundations.

east-harting-house-demolition

Once the site is cleared, a large amount of landscaping is required to lower the ground levels. This means the driveway gradients are much lower and the rear garden will be almost flat when stepping out of the house.

east-harting-house-ground-works

Once the levels are achieved, the footings are dug and the concrete is pumped in, before the slab is then cast.

east-harting-house-concrete-slab

The brick base is then brought up to above damp proof course ready for the timber frame to be erected.

Drainage channels are dug around the house and new pipes laid, ready for connection to the main drainage system.

 

Filed Under: East Harting

  • Home
  • About
  • What We Do
  • Projects
    • Commissions
    • Land Wanted
    • Completed Projects
  • Testimonials
  • Contact Us

Copyright © 2025 The Architectural Building Company ยท Website by Fresh Eyes Agency