East Harting | Weeks 16-20

August 14, 2014 By Rob Hall

Second fix, tiling, kitchen and bathroom fit out, whilst external works continue.

The busy period continues with a host of trades working together as both internal and external works progress towards their conclusion.

Second fix plumbing and electrics follow on from plastering in conjunction with tiling, bathroom and kitchen fit out.

east-harting-house-kitchen-fitout

The oak staircase and ballustrading is installed and final internal joinery including door hanging and wardrobe fitting is completed, whilst the decorators work they way around the house, room by room.

At the end of this period, Kahrs oak flooring and large scale ceramics are laid to the ground floor and carpets to the first floor bedrooms.

east-harting-house-oak-flooring

Externally, the roof is completed, as are the external walls of stone and cedar cladding.

east-harting-house-external-brickwork

 

 

Filed Under: East Harting

  • Home
  • About
  • What We Do
  • Projects
    • Commissions
    • Land Wanted
    • Completed Projects
  • Testimonials
  • Contact Us

Copyright © 2025 The Architectural Building Company ยท Website by Fresh Eyes Agency