East Harting | Weeks 11-15

August 14, 2014 By Rob Hall

First fix, external works and plaster.

This is a really busy time on site with a peak labour force exceeding twenty during this period.

First fix electrics and plumbing are installed, as are the window frames and glazing, whilst external stonework and timber cladding progresses rapidly.

east-harting-house-cedar-cladding

Plastering follows first fix along with internal joinery.

east-harting-house-plastering

At the same time, the underfloor heating system is installed and the system pressure tested before the flooring screed is pumped into the ground floor.

east-harting-house-underfloor-heating

The oak garage structure also takes shape whilst the beautiful stone external garden walls progress.

east-harting-house-timber-garage

east-harting-house-garden-wall

Filed Under: East Harting

  • Home
  • About
  • What We Do
  • Projects
    • Commissions
    • Land Wanted
    • Completed Projects
  • Testimonials
  • Contact Us

Copyright © 2025 The Architectural Building Company ยท Website by Fresh Eyes Agency